New Ryanair Maintenance Hanger Completed...


Practical completion on this £8m project was achieved on 30th August 2010, ahead of programme, with the first planes accessing the facility on the 13th September 2010.

The construction of this fast track project demonstrated the capabilities of our ‘in-house’ design team and through working in close contact with the Client and their advisor we were able to deliver this project from inception to completion in 26 weeks.